The first elements of the new launch rail were brought to the RRS MTA from Colorado. This included the base, modular guide rail and the hydraulic lift system.

Unpacking upon arrival at the RRS MTA
Base mount sitting on the new pad, anchors being made ready

More work to the mounting (bolts) and changes to the hydraulic lift fluid system was necessary. A list of items and tasks were generated for later completion. At this time, the launch rail is not ready for use. Also, the design does not allow the rocket to be mounted and lifted from the horizontal position. The rocket is loaded vertically and attached to the rails by a pair of bellybands similar to the previous launch.

Partial deployment of the new launch rail system, more work required

Launch preparations including mixing, pouring and casting will take place in late April this year as planned. Completing the new launch rail will be added going forward.

Thanks to Joe Dominguez and Rushd Julfiker for their assistance.