MTA Launch Event, 2021-10-16, First Update

by Bill Claybaugh, RRS.ORG


In a remarkable demonstration of persistence and luck, RRS President Osvaldo Tarditti was able to find the spent booster rocket. A few photos were captured of the recovered rocket.

Bill Claybaugh’s recovered spent booster casing brought back to the Mojave Test Area (MTA)
Closeup on the bulkhead shoved into the aluminum case of the booster from the impact.
The fins look great and the nozzle was recovered.

Based on the impact location, it was possible to reconstruct a possible flight trajectory by assuming the motor performed as designed and further assuming the front of the vehicle was a flat plate and that the mass did not include the mass of the payload.  We know from video, telemetry, and recovery of the payload that the payload separated from the booster about one second into the flight.

The recovery location on the map shows a northeast trajectory as confirmed by launch footage.

This analysis suggests a burnout velocity of about 1550 feet/second with a peak altitude of about 21,200 feet given the known range of about 14,300 feet. This analysis gives a flight time of about 74.5 seconds and an impact velocity of about 820 feet/second.

Given the observation that the vehicle stopped in about 2 inches (based on the depth of the depression in the hardpan) before falling on its side; we can estimate the impact deceleration.  Given an average velocity during impact of about 410 feet/second because the final velocity is zero and it took only 0.167 feet to come to rest, it follows that the impact occurred over 0.000407 seconds.  This, in turn, indicates an average deceleration of about 31,250 g’s.

The reason for the vehicle turning to the Northeast starting at about 0.20 seconds into the flight remains unclear. There is no evidence either in video or in images of the recovered hardware of any hot gas leak nor of any transient thrust vector anomaly.  The wind was less than 5 miles per hour and from the Northwest; if it had caused a turn, we would expect it to be toward the Northwest, not the Northeast as observed.  The only plausible theory at this time is that part of the belly-band became embedded between the nose of a fin and the rocket body causing the turn via differential drag and then fell away from the vehicle, causing the resumption of normal flight.  Once the recovered hardware is available for inspection, we will test each fin nose to see if a gap exists that might have caught the 0.020-inch thick belly-band.

The recovered payload segment was examined after it was found just north of the launch site.

It also remains unclear as to why the payload separated about 1 second after launch.  The recovered payload showed that both initiators had fired (by design, if one fires the other is ignited; thus, only one signal is required to fire both) but did not show any evidence of having been “swaged” or otherwise subject to being forced off the rocket by aerodynamic or other forces. Neither does the matching front end of the rocket show any evidence for the payload having been forced off. We thus conclude that one of the flight computers ordered the firing of the initiators.

The bellybands being fit checked in the launch rail.
Recovered bellybands have evidence of tearing from what is likely fin impact.

However, the main flight computer stopped working just after 0.80 seconds into the flight for an unknown reason after recovery it was still connected to its battery, which showed the expected 3.87 volts. Further, the limited data recovered from that computer shows that it did not initiate separation of the payload: the firing circuit shows continuity throughout the period that the computer was operating and separately records that no signal was sent by that computer.

Still image of the rocket just after launch making the unexpected hard turn.

This points to the backup flight computer.  That hardware is currently at the manufacture for repair, after which we hope to extract continuity data with regard to its firing status.  Hopefully, once that and other data is available from the backup computer we will be able to establish when it ordered the separation of the payload, and why.

Recovered payload with the main and backup computer.

A second update to this firing report is expected. The booster has been packaged up for a more detailed inspection.


MTA Launch Event, 2021-09-26


by Keith Yoerg, Reaction Research Society Secretary


The RRS Mojave Test Area (MTA) hosted a launch event and work party on Sunday, September 26th. The USC Rocket Propulsion Lab (USCRPL) had arrived a few days earlier to prepare for a static firing of their 8″ diameter solid rocket motor named “Earthshaker II” which took place on the 26th. Several RRS members also answered the “Yoerg Challenge” to launch model rockets, and Dimitri was out with his water rockets. On the work side of things the Dosa building was re-organized, a security camera was installed, and a discussion began on how best to replace the aging roof on the blockhouse.

USCRPL 8″ SOLID ROCKET STATIC TEST

USCRPL had their setup ready for a static test of their 8″ solid rocket motor in the late afternoon, which was secured below the vertical test stand. Unfortunately, shortly after coming up to full power the motor exploded. All personnel were at a safe distance in the bunker and no one was injured. RRS President and Pyrotechnic Operator in charge Osvaldo approached the site once it was safe and extinguished the resulting flames.

Still shot from a video of the USCRPL motor explosion
Pyrotechnic Operator Osvaldo bringing a fire extinguisher to the lingering fires

All requests to use the RRS MTA must be made to the RRS president and reviewed by the executive council.  For any questions about this test series or any future test series, please contact the RRS president.

president@rrs.org

YOERG CHALLENGE MODEL ROCKET LAUNCHES

Many RRS members had model rockets on hand to answer the “Yoerg Challenge” and launch at the MTA site. Dimitri and his son Max launched a “Helios” and “Dazzler” on C6-3 motors. Keith launched a “Baby Bertha” on a B6-4 and a “Big Bertha” on a B6-2. Dave Nordling launched a “Baby Bertha” on an A motor. Bill Inman & Jon Wells also launched model rocket kits, and John Krell launched a model kit on a G motor. (I will endeavor to do a better job of recording the rockets & motors that everyone uses at these launches for more specific reports in the future).

Keith Yoerg, Bill Inman (on the launch box), Waldo Stakes and Diana Castillo wait as the countdown progresses.

We did not have the new wireless Cobra firing system at the MTA site during this event, so we used the 4-pad controller that Dimitri built earlier this year. The controller split its time between this low-power launch pad and the water rockets which Dimitri had set up on the underground blockhouse.

Several of the model rockets ready to launch on the PVC launch pad built by Keith Yoerg

I will also mention that prior to these launches, we enjoyed a nice potluck BBQ of brats, (homegrown) potato salad, chips, beans, and corn. Several members contributed food which was expertly prepared by Becky. We’ve been doing this more often and seem to keep getting better at it every time!

WORK PARTY TASKS

In addition to the more exciting “fiery” aspects of the day, RRS members also completed a lot of routine maintenance at the MTA site. We completed several general organization tasks in the Dosa Building and the storage containers, and a security camera was installed on the Dosa Building. There was also a lengthy and robust conversation about methods to replace the aging blockhouse roof, which has been high on the the society’s list of desired site improvements for several years.

Keith Yoerg and Jon Wells discuss options for repairing the old blockhouse roof.
Security camera installed on the Dosa Building

September 2021 Virtual Meeting


by Keith Yoerg (RRS Secretary)


The latest meeting of the Reaction Research Society took place Friday, September 10th and had 16 attendees, including several members of the University of Michigan Aeronautical Science Association (MASA) team which conducted a long campaign of testing at our MTA site last month. After brief hellos & a short discussion on updates to this website, we got the meeting rolling with a presentation from the MASA team debriefing us on their August tests.

Screenshot of discussion during the monthly meeting

PRESENTATION ON MASA CAMPAIGN AT THE MTA

4 members of the MASA team who were present for the long campaign of testing at the MTA site were at the meeting and provided a presentation detailing how the nearly 2 weeks of work went for the team. A detailed write-up from RRS member Dave Nordling who was on site assisting for some of that time is available here.

MASA logos – Tangerine Space Machine is named after a craft brewed beer local to the Michigan area

While the end goal of conducting a hot fire test was not accomplished, there was a ton of great work and learning opportunities for both the MASA team and the RRS. The first challenge for the MASA team was in driving their equipment all the way from Michigan to Southern California. Unfortunately, they had some equipment suffer damage during the trip when their smaller “Ground Support Equipment” (GSE) trailer broke through the plywood floor of their larger travel trailer. This required them to stop in Texas and complete repairs to the travel trailer before continuing on to the MTA site.

Once at the site, the MASA team set up a 2-shift schedule (9am – 6pm and 5pm – 12am) effectively working 18-hour days to conduct the activities required for their tests. Many of these tasks took a lot longer than the team had anticipated, in particular with the supply and delivery of the gas & cryogenics needed. The MASA team was originally in contact with Airgas, but their communication was with the office closer to their home in the Midwest and not the Southern California branch. Ultimately sorting through those issues proved to be too difficult to secure a delivery while the team was at the MTA, but fortunately they were able to work with Praxair to secure a supply of the gas and cryo.

MASA presenting a great photo of nighttime work at the MTA to the members at the September meeting

Once the gas and cryogenics were at the site, the team was able to complete pressure tests of the fuel side of the system, and were ultimately able to perform 2 coldflow tests through the entire system near their target pressures. These tests revealed many more areas for design improvements that the team hopes to implement, including reducing fittings, changing the location of vents and drains, and possibly even replacing the LOx and fuel tanks.

Improvements the MASA team hopes to implement

This campaign goes down in the books as the longest to ever take place in RRS history, and proved to be challenging for both the MASA team and the RRS. Several society members graciously volunteered their time to help make this testing effort possible, and the experience revealed many ways that the society could improve our procedures to better support extensive tests like this. Namely: limiting the duration of a test period to no longer than 1 consecutive week, requesting that some members of University staff be on-site when these long campaigns take place, and requiring a longer notice time before approving this sort of test were all brought up by RRS president Osvaldo.

PERMANENT BATHROOM

Progress is continuing on the permanent RRS Bathroom structure. Work on cutting holes for doors and windows has been completed on the 20-foot shipping container and delivery is expected imminently to the new work site at Wilbur’s hangar. The next stages of construction including adding plumbing, fixtures, and the doors and windows, and Osvaldo has already acquired some of these items to install

View from inside the container with the doors and vent windows installed

SEPTEMBER MTA EVENT & WORK PARTY

The USC Rocket Propulsion Lab (USCRPL) plan to be out at the MTA site from Friday, September 24th – Sunday, September 26th to conduct a static fire of an 8″ diameter solid rocket motor. The first few days will consist of prep work and the firing is planned on that Sunday. Several members including Bill Inman and John Krell indicated in the meeting that they have stepped up to the Yoerg Challenge and built model rocket kits to fly at the MTA. This will give us a great excuse to test out the new PVC wire rail launchers as well as the newly purchased Cobra wireless firing system.

In addition, the society has decided to use Sunday, September 26th as the date for our annual “Work Party” to perform maintenance and cleaning tasks at the MTA site. The expected tasks we would like to complete are:

  • Weld the plate on the vertical test stand
  • Removal of dry vegetation
  • Move drum of RP1 (from MASA testing) into one of the lockable containers
  • Fix the 2 broken latches on the Dosa Building roll door
  • Prep/measurements in area for new container bathroom

YOUTH ROCKETRY CLASS

RRS Vice President Frank updated the membership on the upcoming youth rocketry class in Boyle Heights with details on the schedule and overall plan. As opposed to 2 alternating classes, we will now be working with a single class of up to 30 students. The classes will run every Friday starting on September 24th, with a launch planned at the MTA site on November 13th. The plan is for each student to build their own Estes Baby Bertha kit and fly it twice on launch day. RRS Secretary Keith is currently working on 3D printing fin alignment jigs for the students, which will help in both teaching the students about that technology as well as properly installing straight & aligned fins on their rocket kits.

Several of the 3D printed fin alignment jigs

MISCELLANEOUS DISCUSSION

The end of the meeting consisted mostly of miscellaneous discussions around the various projects that RRS members are currently working on. Some of the highlights included John Krell’s new, very small (20x80mm) electronics board capable of collecting 7 channels of data onboard a flight, with over half of those channels at 500 Hz! Bill Inman updated members on the progress with his Solar Cat steam rocket, and there was a brief discussion of ham radio operations with Tom Hendricks sharing some of his wealth of knowledge in that subject. Overall it was a fun meeting with a lot of good discussion & participation from the membership.

NEXT MONTHLY MEETING

The next RRS monthly meeting will be held virtually on Friday, October 8th at 7:30 pm pacific time. Current members will receive an invite via e-mail the week of the meeting. Non-members (or members who have not received recent invites) can request an invitation by sending an email to:

secretary@rrs.org

Please check your spam folders and add secretary@rrs.org to your email whitelist to make sure you receive the invitation.