MTA launch event, 2021-05-01

by Dave Nordling, Reaction Research Society


The Reaction Research Society held an event at the Mojave Test Area (MTA) on May 1, 2021. Dave Crisalli was the pyrotechnic operator in charge. RRS president, Osvaldo Tarditti, was also present along with myself, It was not to be a launch event as all planned tests were static firings by the UCLA liquid rocket team and the UCLA hybrid motor team. The winds were very high that day consistently above 20 MPH and gusts above 50 MPH at times. The weather otherwise was very cooperative with comfortable temperatures.

Other than gusting and persistently hugh winds, it was a great day at the MTA on 5/1/2021

Dave Crisalli gave a safety briefing in the George Dosa building to all attendees before the first static fire campaign would begin. The RRS pyrotechnic operator in charge is responsible for the safety of all during the event. Hazard identification (spiders, snakes, sharp objects) and good practices (hydration, sunscreen) are always part of the briefing, One of the most important things, Dave Crisalli mentioned was not to be in a hurry. It is very important to take the proper time to do things correctly and safely even if it means not proceeding with the intended test that day. Taking your time means avoiding mistakes and improving your chances for success.

Xavier Marshall observes the UCLA hybrid motor controls setup at the RRS MTA on 5/1/2021.

RRS members, Bill Inman and John Wells came to the MTA for the event, but only as spectators. The Solar Cat project is still active and undergoing improvements to its sun tracking method. Bill is also expanding the collector area and adjusting the necessary support structures. It is likely Bill and John will be back for the next RRS MTA event.

Dave Crisalli (left) and Bill Inman (right) at the RRS MTA vertical test stand on 5/1/2021

Also in attendance was the Compton Comet team who have all recently joined the society as members. It was their first time visiting the MTA and getting a chance to see another university team conduct liquid rocket test operations at our vertical test stand.

Members of the Compton Comet team, Manuel Marquez, Aarington Mitchell, Tre Willingham (from left to right) wait at the Observation Bunker at the MTA for the hybrid motor firing with Waldo Stakes (at right).

RRS member, Wolfram Blume came by the RRS MTA to take measurements of the vertical test stand for a future static fire test of his ramjet upper stage engine. He intends to use a leaf-blower compressor motor to simulate foward air flow, but a lot of calculations and planning is required before proceeding. The vertical test stand has a winch and pulley system still attached from Richard Garcia’s liquid motor test in 2017. It should be adequate for Wolfram’s lifting needs when mounting the test equipment to the stand.

The vertical test stand with the winch and pulley system still mounted.

The UCLA team spent the night before on our site setting up their equipment. This advanced planning paid off as they were ready for the first of two hot-fires of the liquid rocket just past noon.

Camera adjustments made before the first hot fire of the UCLA liquid rocket on 5/1/2021

Often, it can take several hours to verify all systems are in good working order before testing especially with a liquid rocket, The hybrid rocket was no exception that day.

The UCLA hybrid motor team installs the fuel grain and nozzle into the 98mm standard motor casing,
The UCLA hybrid motor mounted for static fire on the RRS MTA I-beam

One of the two load cells had failed so the two teams had to share the same load cell between the hybrid motor and liquid motor firings. UCLA chose to let the hybrid team go next after successful results were seen with the first firing, The UCLA hybrid motor team corrected a few issues and were able conduct a successful hot-fire by late afternoon.

The society members in attendance also had time to make some minor repairs to the new mobile trailer asset, A steel plate was added to keep intruders from entering. Thanks to Waldo Stakes for doing the welding for this temporary fix.

The mobile trailer at the RRS MTA needs a lot of repairs

There was sufficient daylight remaining for a second hot-fire of the UCLA liquid rocket, The team had another engine with the previous injector design from last built and ready with a fresh internal ablative liner. They had retanked another load of ethanol and the liquid oxygen cylinder had sufficient stores for another loading cycle.

Preparing for liquid oxygen transfer to the propellant tank

Thanks to the hard-won, acquired experience of the UCLA team and their commitment to training new members and holding to their proven procedures, they were able to conduct the second firing safely for an impressive finish that day.

The UCLA liquid rocket team poses before their liquid rocket after a second successful hot fire on the same day.

Initial data from both UCLA static firings of their liquid motor suggest that the 650 lbf nominal thrust motor outperformed expectations and will be ready for vehicle integration and flight by May 29, 2021. The UCLA team had reason to celebrate at the end of the day. The RRS was glad to be a part of UCLA’s continued campaign to fly liquid rockets that are competitive with any university team in the country.

For other universities interested in working with the RRS, please contact the society president submitting a Standard Record Form downloaded from our website,

president@rrs.org